Commencement of Phase I of Coal Terminal Works in Jinzhou Port
The marine works of Phase I of the coal terminal in
The works includes a wharf and a southern cofferdam. The wharf, which is located at the west end of northern shoreline of the fourth port basin, is a gravity structure made up of 57 caissons and consists of three 70000 dwt specialized coal loading berths which total
The southern cofferdam, which is located at the west end of western coastline of the fourth port basin and totals
The works shall be completed on 20 Feb., 2014 with total construction duration of 611 calendar days. (Zhao Li)