Qingdao Crude Oil Terminal Phase III Works
Qingdao Crude Oil Terminal Phase III Works mainly consists of a designed 300,000.00DWT Terminal for Crude oil loading and offloading with a designed passing capacity of 18,000,000.00DWT. Main structures include approach trestle and wharf in a gravity cylindrical caisson structural type. The diameter is 15.1m and max. height is 33m and the weight per each caisson is 2800t. Total quantity is 33nos. The berth total length is 520m and bottom level is -26.2m. The trestle is 852m long with a cast in-situ prestressed concrete continuous deck as its upper structure. Caisson foundation adopts high pressure mud jacking methodology.
Excellent Prize