Shanghai Pudong International Airport Phase I — Runway Works
Start: May 25th 1997
End: Feb. 8th 1999
The works consists of earthworks in area No.90 and other areas, drainage works, runway surface works, fire fighting pipeline works, preinstalled duct and affiliated facilities.
Shanghai Pudong International Airport Special Parking Lawn Works
Start: Jan.2nd 2001
End: May 22nd 2001
The works total area is 160381m2 including 67265m3 5.0MPa concrete apron, 1308m3 4.5MPa road surfaces and 1365.9m long drainage trench.
Shanghai Pudong International Airport Phase II (the Second Runway) — Fuel Tank Foundation Works
Start: Jun.10th 2004 End: Mar.30th 2005
Shanghai Pudong International Airport Phase II — Linkage Road Earthworks and Foundation Works
Start: April 25th 2004 End: Aug. 28th 2004
Shanghai Pudong International Airport Renovation and Expansion Project — Vacuum Preloading Foundation Treatment Works
Start: Dec.26 2005 End: May 25th 2006
Shanghai Pudong International Airport Renovation and Expansion Project Phase II — Terminal Parking Lot and Affiliated Facility Works (Contract Package I)
Start: Jan. 25th 2006 End: May 25th 2007
Shanghai Pudong International Airport Renovation and Expansion Project
— West Cargo Plane Parking Lawn and Access, and the Third Runway Affiliated Facility Works(Contract Package III)
Start: Mar. 12th 2007 End: Dec.31st 2007
Shanghai Pudong International Airport Renovation and Expansion Project
— Runway No.1 and No.3 Connection Works
Start: Mar. 20th 2007 End: Sept. 20th 2007
Shanghai Pudong International Airport Renovation and Expansion Project Phase I Runway Works was awarded of China Municipal Engineering Gold Trophy in 2000